I.1 Situational reasoning questions

Scenario reference for all questions in this section

A predictive enterprise resource planning (ERP) replacement project is underway in the logistics sector for a multi-warehouse network. Midway through execution, the organization acquires a competitor with a different operating model and margin logic. Senior leadership communication begins to diverge, with some executives emphasizing consolidation and cost efficiency while others continue to press for rapid rollout. No formal plan change has been approved. Local warehouse managers increasingly optimize for local convenience, previously settled decisions are reopened, and steering committee discussions repeat without closure. Work continues, but the original vision no longer gives the project a reliable basis for prioritization.